Switching order boundary samples open jobs on substation and line equipment and confirms none of them are switching. The technician writes the as-found reading and compares it with the last one on the asset. Opening a primary enclosure or operating a switch stops here. Anything past that line belongs to the site's own procedure, the OEM manual, or a permit. This is the inspection ChatterFix schedules. It is not itself permission to go further.

Interval Monthly
Est. Duration 1.0 hr
Steps 5
Applies To Energy & Utilities

The Procedure

The steps ChatterFix schedules for this PM. Every step is a checkable item on the work order — a technician can speak their way through it without touching a keyboard.

  1. Sample open maintenance work orders on substation and line equipment
  2. Confirm none of them open a primary enclosure or operate a switch
  3. Confirm a switching-order path exists and is named, separate from this CMMS task
  4. Check tags in the sample are still on the equipment
  5. Stop a work order that reads like a switching order

Why This PM Exists

Switching order boundary samples open jobs on substation and line equipment and confirms none of them are switching. The technician writes the as-found reading and compares it with the last one on the asset. Opening a primary enclosure or operating a switch stops here. Anything past that line belongs to the site's own procedure, the OEM manual, or a permit. This is the inspection ChatterFix schedules. It is not itself permission to go further.

What Skipping It Looks Like

Tags live in a drawer, and a work order still tells a technician to open the cabinet and look. The round still closes, the number never lands on the asset, and the next person inherits a guess. Opening a primary enclosure or operating a switch stops here.

Setting the interval

Monthly. A job that reads like a switching order is stopped and sent to that procedure. An as-found reading outside the limit the site already published is a finding. It does not become a new setpoint on this work order.

Equipment This Covers

Common Questions

How often should this PM run?
Monthly. Monthly. A job that reads like a switching order is stopped and sent to that procedure. An as-found reading outside the limit the site already published is a finding. It does not become a new setpoint on this work order.
How long does it take?
Budget about 1.0 hour for a technician working to the standard procedure. ChatterFix uses that estimate for capacity planning, then learns your plant's actual time from completed work orders.
What happens if we skip it?
Tags live in a drawer, and a work order still tells a technician to open the cabinet and look. The round still closes, the number never lands on the asset, and the next person inherits a guess. Opening a primary enclosure or operating a switch stops here.
Can I use this checklist in ChatterFix?
Yes — this exact procedure ships in the Energy & Utilities industry pack. Pick your industry at signup and it is scheduled on the right assets automatically, with no configuration.